Processing Your Payment

Please do not leave this page until complete. This can take a few moments.

June 3, 2019

Bitter Dunkin’ Donuts stadium construction lawsuit heads to trial

HBJ File Photo Hartford's Dunkin' Donuts Park, home of the Eastern League Double-A Yard Goats.

A bitter lawsuit between the city of Hartford and the fired former developer of Dunkin’ Donuts Park is finally coming to a head. 

The trial between the city and Centerplan Construction Co./DoNo Hartford LLC, which argues it was wrongfully terminated from the stadium development and is suing for $90 million, is scheduled to start Wednesday, while a pre-trial hearing and jury selection is expected to start today. 

The city hired Centerplan and DoNo Hartford LLC, both controlled by Robert Landino, in early 2015 to oversee development of Dunkin’ Donuts Park, home to the minor-league Double A Hartford Yard Goats baseball team, but the project quickly faced problems.

Faulty construction and other delays created over $10 million in cost overruns that forced the Yard Goats to play its inaugural season entirely on the road.

The city, under the leadership of Mayor Luke Bronin, fired Centerplan and DoNo Hartford LLC in mid-2016, prompting the companies to file a $90 million lawsuit against the city. Performance bond insurer Arch Insurance hired a new contractor to finish the job.

The city filed a counterclaim against Centerplan and DoNo in Oct. 2017, alleging breach of contract, negligence and professional malpractice -- much of it related to alleged defects and deficiencies in the stadium design.

Responding to that countersuit, Centerplan and DoNo denied that they’re liable to the city for any damages suffered as a result of design defects, or that they were negligent with respect to the supervision or management of the design services related to the stadium.

At one point, Centerplan argued that damages the city suffered resulted from negligence, carelessness, omissions or other actions by six design subcontractors. Centerplan and DoNo claimed they performed no design work themselves, and that the design and construction of the stadium were  in the hands of third-party contractors that should have to pay any financial damages that may result.

Despite the ongoing legal dispute, Ballpark Digest has named Dunkin’ Donuts Park the best Double-A ballpark in the country for the past few years.

Meantime, Fairfield County developer Randy Salvatore is eagerly awaiting the go-ahead with his $200 million vision to transform acres of mostly surface parking around the stadium -- known as DoNo -- into a mixed development of apartments, condominiums/townhouses, a supermarket, other retail and office space and a parking garage.

He said in March that his project is nearly shovel ready.

Standing in his way is the lawsuit. Centerplan has placed liens on all the city's DoNo parcels, which means development can't move forward until the case is resolved.

Sign up for Enews

0 Comments

Order a PDF